Date of GRAND OPENING!

Check out our Facebook page for speeches and additional images taken during the event.

4/14/2022


Completed:

Electrical is complete

Plumbing is complete

Pavers installed

Irrigation done

Interior is complete except just waiting on trim to arrive.

Exterior paint done


3/4/2022

Continued parking lot work

Septic system inspected and approved

Polished concrete floors - Completed

Installed flooring/base in gym

RR’s- Completed

Installed RR partitions

Worked on Low Voltage

2/18/2022

Parking lot work

Installed septic tank

Continued finish trim

Finished fireplace wall

Began polishing concrete floor

Prep floor in gym RR’s

2/4/2022

Inspected propane lines

Primed and painted walls

Installed lights in offices

HVAC is on.

Finish electrical

1/21/2022

Installed propane lines

Painting prep

Primed and painted walls

1/14/2022

Worked on final coat on gym floor

HVAC

Painting prep

Applied clear sealer to wood ceilings

1/7/2022

Worked on finishing gym floor

HVAC

Painting prep

12/17/2021

Paint HM Door/Frames

Refinishing Gym Floors

Drywall Taping

Installing HVAC

Installed Storefront Glass

11/19/2021

Installed Insulation

Installed Siding

Continued Parking Lot Work.

Continued Drywall

Cleaned out gym to prep for refinishing.

Permanent power turned on.

Lights are on.

11/5/2021

Installed Insulation

Roughed in Electrical and Plumbing.

Continued Parking Lot Work.

Started Drywall

HVAC

10/29/2021

Continued installing Septic.

Roughed in Electrical and Plumbing.

Continued Parking Lot Work.

Installed Interior Lights.

10/21/2021

Continued installing Septic.

Continued installing roof.

Roughed in Electrical and Plumbing.

Installed Overhead Doors.

Continued Parking Lot Work.

Removed Existing Siding Around Gym.

10/15/2021

Began installing Septic.

Continued installing roof.

Roughed in Electrical.

Installed Metal Doors and Hardware.

Began Parking Lot Work.

Removed Existing Siding Around Gym.

10/7/21

Continued installing stone.

Continued installing roof.

Roughed in Low Voltage.

Installed Storefront Doors in Gym

Detroit 10-7-21 #1 (1).jpg
Detroit 10-7-21 #2 (1).jpg

10/1/21

Continued installing stone.

Continued installing roof.

Installed HM frame

Installed water service.

Installing roof

Detroit 10-1-21 #2.jpg
Detroit 10-1-21 #1.jpg

9/24/2021

Continued electrical rough in.

Continued installing stone.

Installed HM frames.

Installed building wrap.

9/17/2021

Continued electrical rough in.

Began installing stone.

Installed HM frames.

Installed building wrap.

Grouted columns.

Stocked drywall.

Detroit 9-17-21.jpg
Detroit 9-17-21 #3.jpg

8/27/2021

Continued electrical rough in.

Roof framing.

Sheeted roof.

Continued wood framing.

Patched sub floor in gym.

Detroit 8-27-21-#2.jpg
Detroit 8-27-21 #3.jpg
Detroit 8-27-21.jpg

9/8/2021

Continued electrical rough in.

Patched gym flooring.

Installed windows.

Prepped HM door frames.

Install building wrap.

Detroit 9-10-21.jpg
Detroit 9-10-21 #1.jpg
Detroit 9-10-21 #2.jpg

8/27/2021

Continued electrical rough in.

Patched gym flooring.

Installed windows.

Prepped HM door frames.

Install building wrap.

Detroit 8-27-21 #1.jpg
Detroit 8-27-21 #3 (1).jpg
Detroit 8-27-21 (1).jpg

8/20/2021

Continued electrical rough in.

Roof framing

Installed trusses.

Continued wood framing.

Formed/poured pedestals.

Sheeted roof.

Detroit 8-20-21.jpg
Detroit 8-20-21 #2.jpg

8/13/2021

Continued electrical rough in.

Installed ridge beams.

Installing trusses.

Continued wood framing.

Formed pedestals.

Detroit 8-13-21 #1.jpg
Detroit 8-13-21 #2.jpg

8/6/2021

Continued electrical rough in.

Poured more concrete.

Installed steel columns.

Continued wood framing

Detroit 8-6-21 #2.jpg
Detroit 8-6-21.jpg

7/23/21

Installed rebar.

Excavated power trench.

Electrical rough in.

Painting continued in gym.

Detroit 7-23-21 #2.jpg
Detroit 7-23-21.jpg

7/12/2021

Backfilled plumbing trenches.

Brought in 300 tons of rock.

Grading slab area.

Electrical rough in.

Detroit 7-9-21 #5.jpg
Detroit 7-9-21 #2.jpg
Detroit 7-9-21 #1.jpg
Detroit 7-9-21 #3.jpg

6/25/2021

Masonry is topped out.

Excavated for plumbing in existing building.

Filled in existing openings in gym.


6/18/2021

Formed footings.

Completed saw cuts.

CMU up to 20’.

Patched ceilings in gym.

Excavated for plumbing in gym RR area.

Detroit 6-18-21.jpg
Detroit 6-18-21 #1.jpg
Detroit 6-18-21 #2.jpg
Detroit 6-18-21 #3.jpg

6/11/2021

Formed footings.

Filled in walls on existing building.

CMU up to 18’.

Grouted walls at 15’.

Plumbing lay out.

Detroit 6-11-21 #1.jpg
Detroit 6-11-21.jpg

6/10/2021

Exterior walls begin to stack

Gym renovations continue

IMG_7208.JPEG
IMG_7204.JPEG
IMG_7209.JPEG

6/4/2021

Formed footings.

Installed rebar.

CMU up to 10’.

Plumbing lay out.

Detroit 6-4-21 #1.jpg
Detroit 6-4-21 #3.jpg
Detroit 6-4-21 #5.jpg

6/2/21

Some great updates/commitments – this is not a complete list but a great start! I am sure I miss some but working hard to keep track - Rich Duncan

SCE providing copies

CPI provided Temp power hook up

United Rental providing rental equipment

Statewide Fence providing fence rental

ACE Septic providing temp toilet

Owen Construction has the rough grade and build grading complete

Grant Co. Formed and poured footings

Salem Mobile mix provided concrete for footing

Ram Steel provide rebar and steel

Ashland Concrete Cutting providing concrete cutting

Carlson testing Providing on site testing

Murphy Plywood provided 5 units of plywood

Sign Crafters has donated some banners

The GK Machine was able to secure an emergency backup generator at a significant discount

The Detroit Foundation is going after a grant from USDA for the Generator

Pratum Co-op has found a Propane tank for the project

Freres Foundation has Donated the MMP beams and column

Withers has secured 90% of framing materials

          - Looking for Trusses ?

Hardie – providing the siding

Fred Eichler Construction providing Framing

Davidson Masonry Has identified the stone for the exterior Wainscot

Davidson Masonry is providing materials and labor for the Apparatus bay building

Northside Electric with is suppliers has sourced all Electrical materials

          - Looking for Electrician help for install

Salem Heating and Sheet metal secured the HVAC engineering

Working with Salem Heating, Santiam Heating, and Cascade Heating, we are sourcing HVAC package

IIS  Mechanical along with Oregon Cascade and Do It Best and other suppliers we have the Plumbing covered

Mid Valley Commercial has the drywall and ceiling covered

Falls Insulation has the insulation covered

Summit Restoration has cleaned the Gym and is in the process of restoring fixtures

Thomas Kay Flooring is sourcing wood floor repair

LP Painting is painting the Gym

Rodda Paint is providing paint

Integrated solutions NW has committed to the low voltage

Hara’s windows has the vinyl windows

Blackline Glazing has the storefront Covered

Pfeifer Roofing along with Taylor metal has the metal roofing covered

Power Auto Group donated to sponsor the Overhead doors for the Apparatus bays

Salem Sign Co is working on the Score board for the Gym

Salem Sign Co is donating a Flag Pole

AC & Co has donated the Architecture work

Studio 3 Architecture has donated the Rendering work

WSC Engineers has donated the Structural Engineering

AKS Engineers has donated the Civil Engineering

Marion County waived the permit fees to the Foundation as a no profit doing a project for the community

Green Acres Landscape providing landscape drawings

Highway Fuel providing landscape materials

W H Cress Co providing toilet partitions

5/28/21

·         Formed footings.

·         Installed rebar.

·         Special and County inspections.

·         Poured footings.

·         Sawcut interior floor and walls.

Detroit 5-28-21 #3.jpg
Detroit 5-28-21 #1.jpg
Detroit 5-28-21 #5.jpg

5/21/21

·         Placed rock for subgrade and compacted.

·         Continued cleaning in existing building.

·         Layout for plumbing saw cuts.

KIMG1086.JPG
KIMG1088.JPG

5/14/2021

·         Marked out building footprint.

·         Got temp power turned on.

·         Started excavation.

·         Removed existing footings(underground)

·         Continued demo/cleaning in existing building.

·         Layout for plumbing saw cuts.

Detroit 5-14-21 #1.jpg

3/20/21

GROUNDBREAKING!

163285308_10157482906061213_4026151675775474195_n.jpg